College Solar G99 Connections with NGED

G99 grid connection guide for FE college solar projects in NGED's territory: East Midlands, West Midlands, South West, South Wales. Typical timelines, fees, named colleges.

MCS-certifiedG99-experiencedNGED-familiar
What does a NGED G99 college solar connection typically involve?
NGED covers Midlands, South West England, South Wales. Typical G99 timeline for college installs: 13-17 weeks for 200-500 kW G99; 9-13 weeks for 50-200 kW. Fees typically £250-£500 application; £3-12k Network Study where required. Typically the fastest mainland UK DNO. Strong online application portal. Generally low clarification rate for well-prepared applications.
Region
Midlands, South West England, South Wales
Typical timeline
13-17 wk
Application fee
£250-500
Network Study
Above ~400 kW typical

What's distinctive about NGED

Typically the fastest mainland UK DNO. Strong online application portal. Generally low clarification rate for well-prepared applications.

For FE college solar projects in Midlands, South West England, South Wales, this means three planning considerations: (1) start the G99 application within the first 8 weeks of project kickoff — the DNO timeline is typically the critical-path item; (2) factor Network Study fees into the Salix energy savings calculation where installs are above 400 kW; (3) prepare the protection coordination documentation in detail with the design package, which speeds first technical response.

National Grid Electricity Distribution (NGED, formerly WPD) processing performance

⏱️
15 wk
Typical G99 timeline
For 200-500 kW installs
💷
£375 appl
Application fee range mid
Excludes Network Study
🏛️
21
Named FE colleges served
In NGED territory

Practical tips for NGED college solar applications

NGED rebranded from WPD in late 2022 following acquisition by National Grid. Application portal moved to NGED domain. Strong response times — typical first technical response within 7 working days. Pre-application meetings rarely needed under 300 kW.

FE colleges in NGED territory

We've worked with G99 connections for installs at FE colleges across the NGED network. Named providers in this territory include:

Project sequencing with NGED

  1. Week 0-2: Pre-application call with NGED (recommended for installs above 250 kW); confirm point of connection and electrical design baseline.
  2. Week 3-4: Submit G99 application with full design package (single-line diagram, protection scheme, anti-islanding documentation, inverter specification).
  3. Week 5-11: NGED technical review; clarifications addressed within 5-10 working days each round.
  4. Week 12-17: Network Study (if required) and connection agreement issued.
  5. Build phase: Per project programme — physical install scheduled into summer break window.
  6. Commissioning: NGED witness testing — typically a single day; arranged 2-4 weeks after physical commissioning.

Related guides

Accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Commercial Solar Across the UK

For MAT and maintained school solar see solar panels for schools.

For nursing and care home solar see solar panels for care homes.

For NHS trust solar see solar panels for hospitals.

For PCC and diocesan solar see solar panels for churches.

For the UK commercial solar hub visit commercial solar installation.

For UK business solar grants see solar panel grants for businesses.