DNO · NORTH WEST ENGLAND

College Solar G99 Connections with ENW

G99 grid connection guide for FE college solar projects in ENW's territory: Greater Manchester, Cumbria, Lancashire (parts), Cheshire (parts). Typical timelines, fees, named colleges.

MCS-certifiedG99-experiencedENW-familiar
What does a ENW G99 college solar connection typically involve?
ENW covers North West England. Typical G99 timeline for college installs: 13-17 weeks for 200-500 kW G99; 10-13 weeks for 50-200 kW. Fees typically £300-£500 application; £3-15k Network Study where required. Active in voltage rise assessment on weaker network sections; sometimes requires Network Study for installs above 400 kW; strong on protection settings clarification.
Region
North West England
Typical timeline
13-17 wk
Application fee
£300-500
Network Study
Above ~400 kW typical

What's distinctive about ENW

Active in voltage rise assessment on weaker network sections; sometimes requires Network Study for installs above 400 kW; strong on protection settings clarification.

For FE college solar projects in North West England, this means three planning considerations: (1) start the G99 application within the first 8 weeks of project kickoff — the DNO timeline is typically the critical-path item; (2) factor Network Study fees into the Salix energy savings calculation where installs are above 400 kW; (3) prepare the protection coordination documentation in detail with the design package, which speeds first technical response.

Electricity North West (ENW) processing performance

⏱️
15 wk
Typical G99 timeline
For 200-500 kW installs
💷
£400 appl
Application fee range mid
Excludes Network Study
🏛️
9
Named FE colleges served
In ENW territory

Practical tips for ENW college solar applications

Pre-application meetings highly recommended for installs above 250 kW. ENW publishes annual Network Development Plan — useful for flagging upcoming reinforcement work that affects connection capacity.

FE colleges in ENW territory

We've worked with G99 connections for installs at FE colleges across the ENW network. Named providers in this territory include:

Project sequencing with ENW

  1. Week 0-2: Pre-application call with ENW (recommended for installs above 250 kW); confirm point of connection and electrical design baseline.
  2. Week 3-4: Submit G99 application with full design package (single-line diagram, protection scheme, anti-islanding documentation, inverter specification).
  3. Week 5-11: ENW technical review; clarifications addressed within 5-10 working days each round.
  4. Week 12-17: Network Study (if required) and connection agreement issued.
  5. Build phase: Per project programme — physical install scheduled into summer break window.
  6. Commissioning: ENW witness testing — typically a single day; arranged 2-4 weeks after physical commissioning.

Related guides

Accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Commercial Solar Across the UK

For MAT and maintained school solar see solar panels for schools.

For nursing and care home solar see solar panels for care homes.

For NHS trust solar see solar panels for hospitals.