640 kW Multi-Campus Solar — London FE Group Corporation, GLA + Salix Stack

System size
640 kW
Annual saving
£158,000
Payback
4.9 years
Location
Greater London

Scenario

A Greater London FE group corporation formed by a 2019 merger now operates across three campuses spanning two boroughs — a flagship technical and digital campus in inner east London, a construction and engineering campus on a former industrial site in outer east London, and a creative industries campus in inner south London. Combined enrolment runs to roughly 9,400 16-19 learners plus a sizeable adult and apprenticeship cohort.

The corporation’s 2024-25 group electricity bill was £1.42 million. London electricity unit rates have run consistently above the national average, and the corporation’s 2025 strategic plan committed the group to a 60% scope-1+2 emissions reduction against the 2019-20 baseline by 2030 — more aggressive than the AoC Climate Action Roadmap minimum and explicitly designed to dovetail with the GLA Mayor’s net-zero-by-2030 framework.

The estates director and incoming Sustainability Lead — promoted internally from a campus facilities manager role — set out a Climate Action Plan to corporation in autumn 2025 with rooftop solar as the lead intervention across all three sites. The brief from the corporation board: bring in external capital, sequence the build around teaching, and use the scale of the programme to drive unit cost below £900/kW.

This case study is an illustrative composite built from published scheme terms and 2026 London FE group corporation benchmark costs. It does not describe a single real installation.

The modelled design

Total programme: 640 kW across three campuses, designed as a single portfolio bid with phased installation over two summer windows.

  • Technical and digital campus (inner east London): 290 kW (532 × 545 W panels across three connected membrane-roof blocks, 12-14° tilt, two string inverters, 120 kWh battery storage in main plant room to time-shift apprentice evening-class load)
  • Construction and engineering campus (outer east London): 240 kW (440 × 545 W panels across the main workshop and adjacent classroom block, mostly south-aspect, two string inverters, no battery — daytime workshop load consumes generation directly)
  • Creative industries campus (inner south London): 110 kW (200 × 545 W panels across the production-studio block, single string inverter; site constrained by heritage-area planning consent on the front elevation, all panels concealed to rear roof slopes)

Single corporation-wide programme management. DBS-cleared install crews across all three campuses. KCSIE 2025 safeguarding induction at every campus by the campus principal or nominated deputy before any contractor access.

Funding stack — blended GLA + Salix

The unlock on this programme was layering a GLA-backed grant against the Salix Decarbonisation Loan for the residual:

  • Greater London Authority decarbonisation grant: £190,000 (30% of capex), drawn from the GLA’s RE:FIT and Local Energy Accelerator funding streams aligned with London Plan Policy SI 2 and the Mayor’s Solar Action Plan
  • Salix Decarbonisation Loan: £435,000 (residual 70%), 8-year term, £54,375 annual repayment
  • Total capital cost: £625,000 at £977/kW (the heritage-consent constraint at the creative campus added cost vs the portfolio benchmark; without that constraint unit cost would have come in around £915/kW)
  • Modelled annual energy savings: £158,000
  • Year-one net cash position: £103,625 positive (savings minus Salix repayment, no GLA grant repayment)
  • Total 25-year nominal benefit: £2.7m (real-terms model)

The GLA grant application was led by the corporation’s Sustainability Lead with structural support from the group’s deputy CFO; the Salix bid was a single portfolio submission covering the residual. Both funders accepted on first submission inside a combined 14-week window. The corporation board approved the layered package in a single November 2025 minute.

Programme phasing

Summer 2026 (build window 1):

  • Technical and digital campus — 8 weeks scaffold + install + commissioning, including battery integration; commissioned 14 August
  • Creative industries campus — 4 weeks scaffold + install + commissioning; the planning-consent restriction added two design iterations but no programme slippage

Summer 2027 (build window 2):

  • Construction and engineering campus — 8 weeks scaffold + install + commissioning across the workshop and classroom blocks; sequenced to avoid the August T-Level Construction synoptic project window

No teaching cohort across the three campuses lost more than three days of timetabled access to a building during install. The phasing was scoped against the corporation’s combined academic calendar before contract sign and locked in the programme baseline.

Compliance and DNO

  • Three parallel G99 DNO applications across two different DNOs (UK Power Networks east London, UK Power Networks south London — same DNO, two regional design teams). All three accepted inside 16 weeks; the construction campus required a minor export-limiter setting at 200 kW to clear the local network constraint
  • Asbestos R&D survey on the pre-2000 technical and creative campus buildings; Type 3 enclosed protocols needed for two roof penetrations on the inner east campus
  • Structural engineer survey on every roof slope across the three campuses
  • Heritage area planning consent for the creative campus secured at pre-app stage and lodged formally six weeks ahead of design lock
  • KCSIE 2025 safeguarding induction by the campus principal at each campus before any contractor access
  • ESFA Post-16 Audit Code: Salix energy savings calculation and GLA grant drawdown both lodged as auditable workpapers; corporation board minute formally records both elements of the funding stack

Outcomes

  • Year-one actual generation: 6% above design model across the three campuses (weighted average)
  • Year-one actual energy savings: £167,500 versus modelled £158,000 (+6.0%)
  • Battery self-consumption uplift at the technical campus: lifted self-consumption from 71% (PV-only) to 94% with the 120 kWh battery active, capturing the inner-London peak rate spread
  • GLA case study placement — featured in the GLA’s 2027 RE:FIT progress report as a flagship multi-site FE programme
  • EAUC Scorecard: moved the group from “Silver” to “Gold” on the Operations and Estates module on the post-install re-submission
  • AoC Climate Action Plan reporting integration — generation and avoided-emissions feed live into the corporation’s quarterly KPI pack across all three campuses
  • Phase 2 approved November 2026: additional 180 kW at the construction campus on roofs not in the original feasibility, plus integration planning for a 200 kW carport canopy at the technical campus staff/visitor car park

What the Sustainability Lead said

“Going to corporation with a 100% Salix-funded number works for a single college. Going with a 30% GLA grant on top of that completely changes the conversation — it lifted us inside the corporation’s five-year hurdle rate and it positioned the programme inside the Mayor’s net-zero framework, which mattered for our local authority skills-funding relationships. The lesson is to scope the funding stack at the same time as the engineering, not after.”

Cross-references

Every installer we match is accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Free · emailed within 2 working days

Get your college funding & feasibility summary

Tell us about your institution and we'll email a governor-ready funding & feasibility summary: which routes actually apply to you (Salix, PSDS, Great British Energy, mayoral and combined-authority schemes), an indicative system size and capex band worked from your electricity spend, and any red-flag eligibility issues. A desk exercise from what you send — no site visit needed to start.

What we won't do: pass your details to installers without your permission, add you to marketing lists, or ring you out of the blue — we don't even ask for a phone number.

Why we ask what we ask: your spend and postcode set the indicative system size, capex band and which regional schemes you can access — without them the summary would be generic. Reviewed by SEO Dons Editorial. We are an independent advisory, not an installer.