640 kW Multi-Campus Solar — London FE Group Corporation, GLA + Salix Stack

System size
640 kW
Annual saving
£158,000
Payback
4.9 years
Location
Greater London

Scenario

A Greater London FE group corporation formed by a 2019 merger now operates across three campuses spanning two boroughs — a flagship technical and digital campus in inner east London, a construction and engineering campus on a former industrial site in outer east London, and a creative industries campus in inner south London. Combined enrolment runs to roughly 9,400 16-19 learners plus a sizeable adult and apprenticeship cohort.

The corporation’s 2024-25 group electricity bill was £1.42 million. London electricity unit rates have run consistently above the national average, and the corporation’s 2025 strategic plan committed the group to a 60% scope-1+2 emissions reduction against the 2019-20 baseline by 2030 — more aggressive than the AoC Climate Action Roadmap minimum and explicitly designed to dovetail with the GLA Mayor’s net-zero-by-2030 framework.

The estates director and incoming Sustainability Lead — promoted internally from a campus facilities manager role — set out a Climate Action Plan to corporation in autumn 2025 with rooftop solar as the lead intervention across all three sites. The brief from the corporation board: bring in external capital, sequence the build around teaching, and use the scale of the programme to drive unit cost below £900/kW.

This case study is an illustrative composite based on representative London FE group corporation engagements. Specific identifying details are anonymised.

What we delivered

Total programme: 640 kW across three campuses, designed as a single portfolio bid with phased installation over two summer windows.

  • Technical and digital campus (inner east London): 290 kW (532 × 545 W panels across three connected membrane-roof blocks, 12-14° tilt, two string inverters, 120 kWh battery storage in main plant room to time-shift apprentice evening-class load)
  • Construction and engineering campus (outer east London): 240 kW (440 × 545 W panels across the main workshop and adjacent classroom block, mostly south-aspect, two string inverters, no battery — daytime workshop load consumes generation directly)
  • Creative industries campus (inner south London): 110 kW (200 × 545 W panels across the production-studio block, single string inverter; site constrained by heritage-area planning consent on the front elevation, all panels concealed to rear roof slopes)

Single corporation-wide programme management. DBS-cleared install crews across all three campuses. KCSIE 2025 safeguarding induction at every campus by the campus principal or nominated deputy before any contractor access.

Funding stack — blended GLA + Salix

The unlock on this programme was layering a GLA-backed grant against the Salix Decarbonisation Loan for the residual:

  • Greater London Authority decarbonisation grant: £190,000 (30% of capex), drawn from the GLA’s RE:FIT and Local Energy Accelerator funding streams aligned with London Plan Policy SI 2 and the Mayor’s Solar Action Plan
  • Salix Decarbonisation Loan: £435,000 (residual 70%), 8-year term, £54,375 annual repayment
  • Total capital cost: £625,000 at £977/kW (the heritage-consent constraint at the creative campus added cost vs the portfolio benchmark; without that constraint unit cost would have come in around £915/kW)
  • Modelled annual energy savings: £158,000
  • Year-one net cash position: £103,625 positive (savings minus Salix repayment, no GLA grant repayment)
  • Total 25-year nominal benefit: £2.7m (real-terms model)

The GLA grant application was led by the corporation’s Sustainability Lead with structural support from the group’s deputy CFO; the Salix bid was a single portfolio submission covering the residual. Both funders accepted on first submission inside a combined 14-week window. The corporation board approved the layered package in a single November 2025 minute.

Programme phasing

Summer 2026 (build window 1):

  • Technical and digital campus — 8 weeks scaffold + install + commissioning, including battery integration; commissioned 14 August
  • Creative industries campus — 4 weeks scaffold + install + commissioning; the planning-consent restriction added two design iterations but no programme slippage

Summer 2027 (build window 2):

  • Construction and engineering campus — 8 weeks scaffold + install + commissioning across the workshop and classroom blocks; sequenced to avoid the August T-Level Construction synoptic project window

No teaching cohort across the three campuses lost more than three days of timetabled access to a building during install. The phasing was scoped against the corporation’s combined academic calendar before contract sign and locked in the programme baseline.

Compliance and DNO

  • Three parallel G99 DNO applications across two different DNOs (UK Power Networks east London, UK Power Networks south London — same DNO, two regional design teams). All three accepted inside 16 weeks; the construction campus required a minor export-limiter setting at 200 kW to clear the local network constraint
  • Asbestos R&D survey on the pre-2000 technical and creative campus buildings; Type 3 enclosed protocols needed for two roof penetrations on the inner east campus
  • Structural engineer survey on every roof slope across the three campuses
  • Heritage area planning consent for the creative campus secured at pre-app stage and lodged formally six weeks ahead of design lock
  • KCSIE 2025 safeguarding induction by the campus principal at each campus before any contractor access
  • ESFA Post-16 Audit Code: Salix energy savings calculation and GLA grant drawdown both lodged as auditable workpapers; corporation board minute formally records both elements of the funding stack

Outcomes

  • Year-one actual generation: 6% above design model across the three campuses (weighted average)
  • Year-one actual energy savings: £167,500 versus modelled £158,000 (+6.0%)
  • Battery self-consumption uplift at the technical campus: lifted self-consumption from 71% (PV-only) to 94% with the 120 kWh battery active, capturing the inner-London peak rate spread
  • GLA case study placement — featured in the GLA’s 2027 RE:FIT progress report as a flagship multi-site FE programme
  • EAUC Scorecard: moved the group from “Silver” to “Gold” on the Operations and Estates module on the post-install re-submission
  • AoC Climate Action Plan reporting integration — generation and avoided-emissions feed live into the corporation’s quarterly KPI pack across all three campuses
  • Phase 2 approved November 2026: additional 180 kW at the construction campus on roofs not in the original feasibility, plus integration planning for a 200 kW carport canopy at the technical campus staff/visitor car park

What the Sustainability Lead said

“Going to corporation with a 100% Salix-funded number works for a single college. Going with a 30% GLA grant on top of that completely changes the conversation — it lifted us inside the corporation’s five-year hurdle rate and it positioned the programme inside the Mayor’s net-zero framework, which mattered for our local authority skills-funding relationships. The lesson is to scope the funding stack at the same time as the engineering, not after.”

Cross-references

Accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Commercial Solar Across the UK

For MAT and maintained school solar see solar panels for schools.

For nursing and care home solar see solar panels for care homes.

For NHS trust solar see solar panels for hospitals.

For PCC and diocesan solar see solar panels for churches.

For the UK commercial solar hub visit commercial solar installation.

For UK business solar grants see solar panel grants for businesses.