solarpanelsforcolleges

1.6 MW Portfolio Programme Across an 8-Campus FE Group Corporation

System size
1,610 kW + 500 kWh battery across multiple sites
Annual saving
£305,000
Payback
5.2 years
Location
North West & Yorkshire

Scenario

An FE group corporation operating 8 campuses across the North West and Yorkshire — two flagship 12,000 sqm main teaching blocks, four mid-size 6,500–9,000 sqm general FE campuses, and two 2,500 sqm adult and community education annexes — faced a group-wide electricity bill of £4.2m in 2025. The corporation board approved a Climate Action Plan in spring 2026 with a 60% scope-2 reduction commitment by 2032, ahead of the AoC Climate Action Roadmap end-2025 mandate.

The newly appointed Group Sustainability Director — formerly Group Estates Director, with a year of CPD on net zero strategy — led a portfolio feasibility commission. Tendered May 2025; appointed July 2025.

What we delivered

Total programme: 1,610 kW PV across 8 campuses, plus 500 kWh distributed battery storage and EV charging integration on three sites.

CampusBuilding footprintSystem sizeNotes
Flagship 1 (North West)12,000 sqm320 kWMain teaching block + sports hall
Flagship 2 (Yorkshire)12,000 sqm290 kWMain block + workshop annex
Mid 19,000 sqm220 kWMixed-use teaching + workshop
Mid 28,500 sqm200 kWSixth form-style centre
Mid 37,200 sqm200 kWEngineering and motor vehicle
Mid 46,500 sqm180 kWConstruction and trades workshop
Annex 12,500 sqm95 kWACE delivery centre
Annex 22,500 sqm75 kWAdult and family learning

Battery storage: 500 kWh distributed across the two flagship campuses (250 kWh each). EV charging integration on the two flagships and one mid-size campus.

Funding structure

Blended Salix + PSDS to maximise capital recovery at portfolio scale:

  • Salix Decarbonisation Loan (70%): £917,000 over 10 years at £92,000/year repayment. Salix accepted a single bid for the whole portfolio, with energy savings calculations rolled up at the group level and a single corporation board approval minute.
  • PSDS Phase 4 (30%): £393,000 capital grant — paired with air-source heat pump installs on three of the campuses, funded under the same PSDS bid. The combined heat-plus-PV portfolio scored in the top 8% of Phase 4 bids in the round.
  • Total project capex: £1,310,000 at £815/kW — portfolio-scale unit cost
  • Modelled annual group-wide energy savings: £305,000
  • Net cash-flow positive year one: £213,000/year

The Group Director of Finance later commented that the single-bid Salix approach saved the team an estimated 4-5 months of paperwork that would otherwise have been required across 8 separate campus-by-campus applications.

Programme phasing

Three summer break windows for the full portfolio:

  • Summer 2026 (window 1): Flagship 1 + Annex 1 + Mid 4 (3 sites)
  • Summer 2027 (window 2): Flagship 2 + Mid 1 + Mid 3 (3 sites)
  • Summer 2028 (window 3): Mid 2 + Annex 2 + battery commissioning at flagships + EV infrastructure (2 sites + integration work)

No campus had more than 6 weeks of disruption to one summer’s apprentice EPAs, T-Level synoptic blocks, or A-level exams. Group-wide academic calendar visibility was set up at contract signature.

Compliance

  • KCSIE 2025 safeguarding induction at every campus; DBS-cleared crews throughout
  • ESFA Post-16 Audit Code — group-level capital reporting accommodating the portfolio programme
  • Listed Building Consent on one of the mid-size campuses (Grade II main building inherited under incorporation) — added 12 weeks to that campus’s timeline; managed within the wider phasing
  • G99 DNO applications across 8 campuses in parallel — coordinated through a single DNO liaison
  • Asbestos R&D survey on every pre-2000 building; one campus required Type 3 enclosed protocols on three roof penetrations
  • Skills England transition (June 2025) — project rationale formally tied to T-Level Green Skills curriculum delivery across all 8 campuses

Outcomes

  • Year one (campuses commissioned by end of summer 2026): generation 6% above design model; energy savings 8% above model thanks to higher-than-modelled self-consumption rates from concurrent T-Level Construction and Engineering workshop expansion
  • Featured in the AoC annual conference as case study — keynote panel session
  • Group-wide live-generation dashboard live at the group head office and at every campus reception
  • T-Level Green Skills cohorts across all 8 campuses ran joint synoptic projects on the install data — a coordinated curriculum initiative that won the group a Skills England innovation award
  • Group apprenticeship marketing referenced the install in 2027 prospectus
  • Phase 2 conversations opened on adding solar to the remaining two campuses (acquired post-feasibility) in 2028-29

What the Group Sustainability Director said

“At group scale the unit economics simply work. Portfolio-scale procurement got us to £815/kW installed where single-site work would have been £950/kW or higher. One Salix bid covered everything — saved my team 5 months of paperwork. One DNO liaison ran 8 G99 applications in parallel. One commissioning protocol applied across the whole portfolio. We could have done this campus by campus and it would have taken 4 years. Doing it as a group programme it took 30 months from first call to last commissioning.”

Cross-references

Accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Commercial Solar Across the UK

Visit the UK hub for commercial solar installation.