1.6 MW Portfolio Programme Across an 8-Campus FE Group Corporation
- System size
- 1,610 kW + 500 kWh battery across multiple sites
- Annual saving
- £305,000
- Payback
- 5.2 years
- Location
- North West & Yorkshire
Modelled example, not a completed installation. The college, people and figures below are illustrative and built from published scheme terms and benchmark costs; no named college or client is described. The funding stack shows how the schemes worked: as of 20 October 2026 PSDS Phase 4 is closed to new applications and Salix has no scheme open for England.
Scenario
An FE group corporation operating 8 campuses across the North West and Yorkshire — two flagship 12,000 sqm main teaching blocks, four mid-size 6,500–9,000 sqm general FE campuses, and two 2,500 sqm adult and community education annexes — faced a group-wide electricity bill of £4.2m in 2025. The corporation board approved a Climate Action Plan in spring 2026 with a 60% scope-2 reduction commitment by 2032, ahead of the AoC Climate Action Roadmap end-2025 mandate.
The newly appointed Group Sustainability Director — formerly Group Estates Director, with a year of CPD on net zero strategy — led a portfolio feasibility commission. Tendered May 2025; appointed July 2025.
This case study is an illustrative composite built from published scheme terms and 2026 sector benchmark costs. It does not describe a single real installation.
The modelled design
Total programme: 1,610 kW PV across 8 campuses, plus 500 kWh distributed battery storage and EV charging integration on three sites.
| Campus | Building footprint | System size | Notes |
|---|---|---|---|
| Flagship 1 (North West) | 12,000 sqm | 320 kW | Main teaching block + sports hall |
| Flagship 2 (Yorkshire) | 12,000 sqm | 290 kW | Main block + workshop annex |
| Mid 1 | 9,000 sqm | 220 kW | Mixed-use teaching + workshop |
| Mid 2 | 8,500 sqm | 200 kW | Sixth form-style centre |
| Mid 3 | 7,200 sqm | 200 kW | Engineering and motor vehicle |
| Mid 4 | 6,500 sqm | 180 kW | Construction and trades workshop |
| Annex 1 | 2,500 sqm | 95 kW | ACE delivery centre |
| Annex 2 | 2,500 sqm | 75 kW | Adult and family learning |
Battery storage: 500 kWh distributed across the two flagship campuses (250 kWh each). EV charging integration on the two flagships and one mid-size campus.
Funding structure
Blended Salix + PSDS to maximise capital recovery at portfolio scale:
- Salix Decarbonisation Loan (70%): £917,000 over 10 years at £92,000/year repayment. Salix accepted a single bid for the whole portfolio, with energy savings calculations rolled up at the group level and a single corporation board approval minute.
- PSDS Phase 4 (30%): £393,000 capital grant — paired with air-source heat pump installs on three of the campuses, funded under the same PSDS bid. Bundling heat pumps with PV raises the carbon saved per pound of grant, which is how PSDS scored bids.
- Total project capex: £1,310,000 at £815/kW — portfolio-scale unit cost
- Modelled annual group-wide energy savings: £305,000
- Net cash-flow positive year one: £213,000/year
The Group Director of Finance later commented that the single-bid Salix approach saved the team an estimated 4-5 months of paperwork that would otherwise have been required across 8 separate campus-by-campus applications.
Programme phasing
Three summer break windows for the full portfolio:
- Summer 2026 (window 1): Flagship 1 + Annex 1 + Mid 4 (3 sites)
- Summer 2027 (window 2): Flagship 2 + Mid 1 + Mid 3 (3 sites)
- Summer 2028 (window 3): Mid 2 + Annex 2 + battery commissioning at flagships + EV infrastructure (2 sites + integration work)
No campus had more than 6 weeks of disruption to one summer’s apprentice EPAs, T-Level synoptic blocks, or A-level exams. Group-wide academic calendar visibility was set up at contract signature.
Compliance
- KCSIE 2025 safeguarding induction at every campus; DBS-checked crews throughout
- ESFA Post-16 Audit Code — group-level capital reporting accommodating the portfolio programme
- Listed Building Consent on one of the mid-size campuses (Grade II main building inherited under incorporation) — added 12 weeks to that campus’s timeline; managed within the wider phasing
- G99 DNO applications across 8 campuses in parallel — coordinated through a single DNO liaison
- Asbestos R&D survey on every pre-2000 building; one campus required Type 3 enclosed protocols on three roof penetrations
- Skills England transition (June 2025) — project rationale formally tied to T-Level Green Skills curriculum delivery across all 8 campuses
Outcomes
- Year one (campuses commissioned by end of summer 2026): generation 6% above design model; energy savings 8% above model thanks to higher-than-modelled self-consumption rates from concurrent T-Level Construction and Engineering workshop expansion
- Featured in the AoC annual conference as case study — keynote panel session
- Group-wide live-generation dashboard live at the group head office and at every campus reception
- T-Level Green Skills cohorts across all 8 campuses ran joint synoptic projects on the install data — a coordinated curriculum initiative that won the group a Skills England innovation award
- Group apprenticeship marketing referenced the install in 2027 prospectus
- Phase 2 conversations opened on adding solar to the remaining two campuses (acquired post-feasibility) in 2028-29