Salix Decarbonisation Loan Bid Timeline Week-by-Week — 14-Week Template for FE Colleges

Week-by-week 14-week Salix Decarbonisation Loan bid timeline for FE corporations — from HHD data pull (week 0) to signed loan offer (week 14).

SEO Dons Editorial — min read fundingsalixbid-timeline

Most FE corporations underestimate the calendar work involved in a successful Salix Decarbonisation Loan bid. The application form itself is tractable in a fortnight; the real timeline is the evidence pipeline behind it — the half-hourly demand data, the structural sign-off, the DNO conversation, the governor approval window. Pull any one of these out of sequence and the bid slips a quarter.

This is the 14-week template we use with FE Sustainability Leads, ordered backwards from the moment the loan offer needs signing. Adjust by ±2 weeks for college-specific governance cycles.

The fast answer

A clean Salix bid for an FE college solar project runs 14 working weeks from kick-off to signed loan offer, assuming no committee misses. The critical-path items are the half-hourly demand (HHD) pull (week 0), the structural roof survey (week 4), the G99 pre-application to the DNO (week 5), the governor Finance & Resources Committee sign-off (week 11), and the Salix portal submission window (week 12). Everything else can flex by a fortnight; these five cannot.

Week-by-week breakdown

Week 0 — Trigger and data pull

  • Sustainability Lead pulls 12 months of half-hourly demand (HHD) data from the supplier or MOP for every meter point in scope
  • Confirm corporation is in scope (ONS-reclassified FE corporation, since November 2022 — see Salix vs PSDS Phase 4 — which route?)
  • Decide whether this is a single-site or multi-site bid (Salix accepts bundled multi-site bids if all sites share a corporation)

Weeks 1-2 — Internal scoping

  • Sustainability Lead + Estates Director walk every candidate roof: pitch, orientation, structural age, last refurbishment date
  • Pre-2000 buildings get logged for asbestos and structural survey prioritisation
  • Director of Finance gets a one-page heads-up: indicative project size, draw schedule, payback range

Week 3 — Specialist appointment

  • Appoint an MCS-certified commercial solar installer with FE track record. The corporation usually goes through the CCS RM6011 framework here to avoid a full OJEU process
  • Installer prepares an indicative system design, generation model, and 25-year cashflow

Week 4 — Structural surveys (critical path)

  • Independent structural engineer surveys every candidate roof
  • Loadings calculated for proposed array weight (typically 12-18 kg/m² for ballasted, 8-12 kg/m² for penetration-fixed)
  • This is the gating step: without sign-off, no installer will quote firmly and no underwriter will commit

Week 5 — DNO pre-application (critical path)

  • G99 pre-application to the District Network Operator covering the full proposed export capacity
  • Lead time is typically 4-8 weeks for a response. This is why it must start by week 5 — see G99 DNO application timeline
  • If the DNO comes back with grid reinforcement costs, those must be built into the Salix bid before submission

Week 6 — Firm quote and generation model

  • Installer issues firm quote (not indicative) with payment schedule
  • Independent generation model from a third party (PVSyst, Solcast, or installer’s modelled output validated by an MCS designer)
  • Director of Finance reviews the cashflow and confirms the draw schedule fits the corporation’s working capital position

Week 7 — Bid document drafting

  • Sustainability Lead drafts the Salix bid narrative: project description, decarbonisation metric (kgCO2e/£), payback, alignment with the corporation’s AoC Climate Action Plan
  • Carbon savings calculated per Salix’s published carbon factors (currently 0.207 kgCO2e/kWh for grid electricity displaced)

Week 8 — Internal QA

  • SLT review of bid draft
  • Estates Director signs off the technical evidence pack (structural survey, G99 response, firm quote)
  • Director of Finance signs off the financial annex (draw schedule, repayment profile, balance sheet impact)

Weeks 9-10 — Governance pipeline

  • Finance & Resources Committee paper drafted and circulated 10 working days before the meeting
  • Committee meeting itself: decision logged in minutes
  • If the loan exceeds the corporation’s standing financial instructions threshold (typically £500k), it also needs full Board approval

Week 11 — Governor sign-off (critical path)

  • Either Finance & Resources or full Board (per delegation thresholds) approves the borrowing
  • Signed minute issued — Salix needs sight of this before they will release the loan offer

Week 12 — Salix portal submission (critical path)

  • Bid uploaded to the Salix Energy Efficiency Loans portal with all annexes:
    • Firm installer quote
    • Generation model
    • Structural survey
    • G99 pre-application response
    • Half-hourly demand baseline (12 months)
    • Governor approval minute
    • Carbon savings calculation worksheet
    • 25-year cashflow with discount rate stated

Week 13 — Salix review

  • Salix typically responds in 2-4 weeks with either a loan offer or a clarification request
  • Clarifications most commonly relate to the displaced-carbon calculation (Salix wants methodology, not just the answer) or the draw schedule (they prefer milestone-based against installation completion)

Week 14 — Loan offer signed

  • Director of Finance signs the loan offer
  • Drawdown schedule confirmed in writing
  • Project moves from funding workstream to delivery workstream

What slips this timeline most often

In our experience supporting FE corporations through Salix bids, the timeline slips in four predictable places:

Slip causeTypical delayHow to avoid
Structural survey unavailable3-4 weeksBook the survey in week 1, not week 4 — they get diary-locked fast
DNO G99 response delay4-8 weeks beyond the 5-week assumptionSubmit a “minded to apply” indicative request alongside week-0 data, not formally but to flag intent
F&R Committee misses a sitting6-8 weeks (next quarterly meeting)Map the Salix bid backwards from the F&R calendar at week 0, not week 9
Salix clarification request2-3 weeks per roundPre-empt by including a methodology annex on carbon savings (most common clarification)

When the 14-week timeline doesn’t apply

For multi-site bundled bids covering more than three campuses, add 3-4 weeks for the additional structural surveys and the consolidation of multiple G99 responses into one bid narrative. For bids over £1.5m capital, add 2 weeks for the additional financial scrutiny Salix runs on larger schemes. For projects that bundle solar with battery storage, add 2 weeks for the additional independent generation/dispatch modelling and the DNO conversation on export limiting.

If you’re choosing between Salix and PSDS Phase 4, the PSDS timeline is longer (typically 20+ weeks because the bid window is fixed rather than rolling) — see the PSDS Phase 4 bid checklist and the PSDS Phase 4 page for the parallel timeline.

SEO Dons Editorial
FE Sector Editorial Team

The solarpanelsforcolleges.co.uk editorial team — specialist writers covering UK FE college solar PV, Salix Decarbonisation Loan applications, PSDS Phase 4 bid mechanics, AoC Climate Action Plan delivery, T-Level Capital integration, and the wider net-zero policy landscape affecting the UK Further Education sector. Combined coverage across 200+ guides, 26 blog posts, and 15 named-college estate assessments.

Specialist topics
  • Salix Decarbonisation Loan bid mechanics
  • PSDS Phase 4 scoring and bundled bids
  • AoC Climate Action Roadmap implementation
  • FE Capital Transformation Fund + T-Level Capital integration
  • ESFA Post-16 Audit Code compliance
  • EAUC Sustainability Leadership Scorecard reporting

Accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Commercial Solar Across the UK

For MAT and maintained school solar see solar panels for schools.

For nursing and care home solar see solar panels for care homes.

For NHS trust solar see solar panels for hospitals.

For PCC and diocesan solar see solar panels for churches.

For the UK commercial solar hub visit commercial solar installation.

For UK business solar grants see solar panel grants for businesses.