Salix Decarbonisation Loan Bid Timeline Week-by-Week — 14-Week Template for FE Colleges

Week-by-week 14-week Salix Decarbonisation Loan bid timeline for FE corporations — from HHD data pull (week 0) to signed loan offer (week 14).

SEO Dons Editorial — min read fundingsalixbid-timeline

Most FE corporations underestimate the calendar work involved in a successful Salix Decarbonisation Loan bid. The application form itself is tractable in a fortnight; the real timeline is the evidence pipeline behind it — the half-hourly demand data, the structural sign-off, the DNO conversation, the governor approval window. Pull any one of these out of sequence and the bid slips a quarter.

This is the 14-week template we use with FE Sustainability Leads, ordered backwards from the moment the loan offer needs signing. Adjust by ±2 weeks for college-specific governance cycles.

The fast answer

A clean Salix bid for an FE college solar project runs 14 working weeks from kick-off to signed loan offer, assuming no committee misses. The critical-path items are the half-hourly demand (HHD) pull (week 0), the structural roof survey (week 4), the G99 pre-application to the DNO (week 5), the governor Finance & Resources Committee sign-off (week 11), and the Salix portal submission window (week 12). Everything else can flex by a fortnight; these five cannot.

Week-by-week breakdown

Week 0 — Trigger and data pull

  • Sustainability Lead pulls 12 months of half-hourly demand (HHD) data from the supplier or MOP for every meter point in scope
  • Confirm corporation is in scope (ONS-reclassified FE corporation, since November 2022 — see Salix vs PSDS Phase 4 — which route?)
  • Decide whether this is a single-site or multi-site bid (Salix accepts bundled multi-site bids if all sites share a corporation)

Weeks 1-2 — Internal scoping

  • Sustainability Lead + Estates Director walk every candidate roof: pitch, orientation, structural age, last refurbishment date
  • Pre-2000 buildings get logged for asbestos and structural survey prioritisation
  • Director of Finance gets a one-page heads-up: indicative project size, draw schedule, payback range

Week 3 — Specialist appointment

  • Appoint an MCS-certified commercial solar installer with FE track record. The corporation usually goes through the CCS RM6011 framework here to avoid a full OJEU process
  • Installer prepares an indicative system design, generation model, and 25-year cashflow

Week 4 — Structural surveys (critical path)

  • Independent structural engineer surveys every candidate roof
  • Loadings calculated for proposed array weight (typically 12-18 kg/m² for ballasted, 8-12 kg/m² for penetration-fixed)
  • This is the gating step: without sign-off, no installer will quote firmly and no underwriter will commit

Week 5 — DNO pre-application (critical path)

  • G99 pre-application to the District Network Operator covering the full proposed export capacity
  • Lead time is typically 4-8 weeks for a response. This is why it must start by week 5 — see G99 DNO application timeline
  • If the DNO comes back with grid reinforcement costs, those must be built into the Salix bid before submission

Week 6 — Firm quote and generation model

  • Installer issues firm quote (not indicative) with payment schedule
  • Independent generation model from a third party (PVSyst, Solcast, or installer’s modelled output validated by an MCS designer)
  • Director of Finance reviews the cashflow and confirms the draw schedule fits the corporation’s working capital position

Week 7 — Bid document drafting

  • Sustainability Lead drafts the Salix bid narrative: project description, decarbonisation metric (kgCO2e/£), payback, alignment with the corporation’s AoC Climate Action Plan
  • Carbon savings calculated per Salix’s published carbon factors (currently 0.207 kgCO2e/kWh for grid electricity displaced)

Week 8 — Internal QA

  • SLT review of bid draft
  • Estates Director signs off the technical evidence pack (structural survey, G99 response, firm quote)
  • Director of Finance signs off the financial annex (draw schedule, repayment profile, balance sheet impact)

Weeks 9-10 — Governance pipeline

  • Finance & Resources Committee paper drafted and circulated 10 working days before the meeting
  • Committee meeting itself: decision logged in minutes
  • If the loan exceeds the corporation’s standing financial instructions threshold (typically £500k), it also needs full Board approval

Week 11 — Governor sign-off (critical path)

  • Either Finance & Resources or full Board (per delegation thresholds) approves the borrowing
  • Signed minute issued — Salix needs sight of this before they will release the loan offer

Week 12 — Salix portal submission (critical path)

  • Bid uploaded to the Salix Energy Efficiency Loans portal with all annexes:
    • Firm installer quote
    • Generation model
    • Structural survey
    • G99 pre-application response
    • Half-hourly demand baseline (12 months)
    • Governor approval minute
    • Carbon savings calculation worksheet
    • 25-year cashflow with discount rate stated

Week 13 — Salix review

  • Salix typically responds in 2-4 weeks with either a loan offer or a clarification request
  • Clarifications most commonly relate to the displaced-carbon calculation (Salix wants methodology, not just the answer) or the draw schedule (they prefer milestone-based against installation completion)

Week 14 — Loan offer signed

  • Director of Finance signs the loan offer
  • Drawdown schedule confirmed in writing
  • Project moves from funding workstream to delivery workstream

What slips this timeline most often

In our experience supporting FE corporations through Salix bids, the timeline slips in four predictable places:

Slip causeTypical delayHow to avoid
Structural survey unavailable3-4 weeksBook the survey in week 1, not week 4 — they get diary-locked fast
DNO G99 response delay4-8 weeks beyond the 5-week assumptionSubmit a “minded to apply” indicative request alongside week-0 data, not formally but to flag intent
F&R Committee misses a sitting6-8 weeks (next quarterly meeting)Map the Salix bid backwards from the F&R calendar at week 0, not week 9
Salix clarification request2-3 weeks per roundPre-empt by including a methodology annex on carbon savings (most common clarification)

When the 14-week timeline doesn’t apply

For multi-site bundled bids covering more than three campuses, add 3-4 weeks for the additional structural surveys and the consolidation of multiple G99 responses into one bid narrative. For bids over £1.5m capital, add 2 weeks for the additional financial scrutiny Salix runs on larger schemes. For projects that bundle solar with battery storage, add 2 weeks for the additional independent generation/dispatch modelling and the DNO conversation on export limiting.

If you’re choosing between Salix and PSDS Phase 4, the PSDS timeline is longer (typically 20+ weeks because the bid window is fixed rather than rolling) — see the PSDS Phase 4 bid checklist and the PSDS Phase 4 page for the parallel timeline.

SEO Dons Editorial
FE Sector Editorial Team

The solarpanelsforcolleges.co.uk editorial team — specialist writers covering UK FE college solar PV, Salix Decarbonisation Loan applications, PSDS Phase 4 bid mechanics, AoC Climate Action Plan delivery, T-Level Capital integration, and the wider net-zero policy landscape affecting the UK Further Education sector. Combined coverage across 200+ guides, 26 blog posts, and 15 named-college estate assessments.

Specialist topics
  • Salix Decarbonisation Loan bid mechanics
  • PSDS Phase 4 scoring and bundled bids
  • AoC Climate Action Roadmap implementation
  • FE Capital Transformation Fund + T-Level Capital integration
  • ESFA Post-16 Audit Code compliance
  • EAUC Sustainability Leadership Scorecard reporting

Every installer we match is accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Free · emailed within 2 working days

Get your college funding & feasibility summary

Tell us about your institution and we'll email a governor-ready funding & feasibility summary: which routes actually apply to you (Salix, PSDS, Great British Energy, mayoral and combined-authority schemes), an indicative system size and capex band worked from your electricity spend, and any red-flag eligibility issues. A desk exercise from what you send — no site visit needed to start.

What we won't do: pass your details to installers without your permission, add you to marketing lists, or ring you out of the blue — we don't even ask for a phone number.

Why we ask what we ask: your spend and postcode set the indicative system size, capex band and which regional schemes you can access — without them the summary would be generic. Reviewed by SEO Dons Editorial. We are an independent advisory, not an installer.