Year-One Implementation Checklist for FE College Solar Projects

Month-by-month delivery checklist for an FE Sustainability Lead delivering the first year of a college solar programme — from board approval to commissioning.

SEO Dons Editorial — min read implementationproject-managementyear-one

Twelve months from board approval to commissioning is the standard timeline for an FE college solar project. Here’s the month-by-month checklist that successful Sustainability Leads work through.

Month 1 — Foundation

  • Corporation board approval minute formally recorded
  • Sustainability Lead role and reporting line confirmed in writing
  • Project budget allocation confirmed (Salix + any matched funding)
  • Project Director identified (typically Director of Estates or Director of Finance)
  • Sustainability Committee composition confirmed (Principal/CEO, Director of Finance, Director of Estates, Student Union rep, external sustainability expert)
  • First Sustainability Committee meeting scheduled

Month 2 — Feasibility kick-off

  • Half-hourly meter data pulled from the corporation’s electricity supplier (12 months minimum)
  • Structural engineer survey commissioned for every campus and every roof slope
  • Asbestos R&D survey commissioned where pre-2000 estate is involved
  • Solar feasibility partner appointed (us, ideally)
  • Feasibility scope confirmed — system sizing, sub-vertical analysis, funding stack mapping, DNO assessment

Month 3 — Design and bid drafting

  • Feasibility report received and reviewed
  • Design package finalised — system size, panel manufacturer, inverter manufacturer, mounting system, electrical design, monitoring platform
  • G99 DNO application initiated
  • Salix Decarbonisation Loan application drafted
  • Corporation board paper drafted for project approval
  • Procurement strategy confirmed (direct award, framework, competitive tender)

Month 4 — Approvals

  • Corporation board paper presented and approved
  • Salix application submitted
  • PSDS Phase 4 bid prepared (if bundling with heat decarbonisation)
  • Procurement process initiated
  • Communications plan briefed to internal stakeholders (Principal/CEO, learner-facing teams, marketing)

Month 5 — Salix and PSDS responses

  • Salix loan offer received (typically 6-10 weeks from submission)
  • Salix loan contract signed
  • PSDS bid scoring confirmed (if applicable; rolling rounds)
  • G99 DNO progress check — confirm timeline alignment with planned install date
  • Communications: announce project to learner body and staff

Month 6 — Procurement complete

  • Installer appointed and contracted
  • Build programme finalised aligned with academic calendar
  • Insurance, warranty, and post-install monitoring contracts confirmed
  • Site security and access protocols agreed with estates team
  • DBS clearance confirmed for all install crew
  • KCSIE safeguarding induction scheduled

Month 7 — Pre-build mobilisation

  • G99 connection agreement issued by DNO
  • Final structural and asbestos reports issued
  • Listed Building Consent in place (if applicable)
  • Site setup briefing with installer
  • Scaffold provider mobilised
  • Disruption windows confirmed per campus (exam periods, T-Level synoptic blocks, EPA windows)

Month 8 — Physical install (summer break window 1)

  • Scaffold erection complete
  • Mounting system installation
  • Panel delivery and installation
  • Inverter installation
  • Battery installation (if applicable)
  • DC and AC electrical first fix
  • Weekly site supervisor reports to Sustainability Lead

Month 9 — Commissioning

  • Electrical commissioning by MCS-certified contractor
  • DNO witness testing scheduled
  • Final safety certifications issued
  • Monitoring platform integration with corporation IT
  • Live-generation dashboard install in main entrance
  • Classroom data feed for T-Level Green Skills cohorts configured

Month 10 — Go-live

  • DNO commissioning visit and connection agreement final sign-off
  • Smart Export Guarantee licensee registered (Octopus Outgoing, E.ON Next Export Exclusive, etc.)
  • First grid-connected operation
  • AoC Climate Action Plan evidence pack delivered
  • Curriculum tie-in: first lesson sequence using live data
  • Press release and social media announcement

Month 11 — Post-commissioning review

  • First-month generation review (actual vs modelled)
  • Salix first repayment scheduled
  • SEG first export payment received
  • Sustainability Committee review meeting
  • EAUC Sustainability Leadership Scorecard data populated
  • Open day demonstration prepared

Month 12 — Year-1 closing

  • Year-1 performance review against feasibility model
  • Variance analysis (any divergence >10% formally reported)
  • AoC Climate Action Plan annual progress update drafted
  • Corporation board update with year-1 outcomes
  • Year-2 project scoping initiated (likely heat pump + further PV)
  • Lessons-learned register updated

Common slippage points

Five places where year-one projects most often slip:

  1. DNO G99 timeline. Underestimated as a 4-6 week process; actually 12-18 weeks. Start in month 3, not month 6.
  2. Salix application quality. Conservative energy savings calculation is approved fast; aspirational claims trigger clarification rounds that add 4-8 weeks.
  3. Corporation board approval cycle. Some corporations have quarterly board meetings — missing the cycle adds 3 months of slippage.
  4. Asbestos discovery. Type 3 enclosed protocols add 3-4 weeks and £15-25k to project. Plan for the possibility on pre-2000 estate.
  5. Term-time install attempts. Disrupts teaching, generates governance friction, slows the project. Always sequence physical install into summer break window.

What “good” looks like at end of year 1

A successful first year of an FE solar programme delivers:

  • Single-site project commissioned and grid-connected with verified positive year-one net cash position
  • Live-generation dashboard operating in main entrance with classroom data feed
  • AoC Climate Action Plan evidence pack drops cleanly into the corporation’s annual report
  • EAUC Sustainability Leadership Scorecard first return populated with real data
  • Lessons-learned register ready to inform year-2 scope (typically heat pump + further PV)
  • Internal communications momentum — learner body, staff, parents and Sustainability Committee all aware of the asset

The corporation board has been delivered a tangible, visible, financially positive intervention against the Climate Action Plan target. Years 2-5 build on that foundation.

SEO Dons Editorial
FE Sector Editorial Team

The solarpanelsforcolleges.co.uk editorial team — specialist writers covering UK FE college solar PV, Salix Decarbonisation Loan applications, PSDS Phase 4 bid mechanics, AoC Climate Action Plan delivery, T-Level Capital integration, and the wider net-zero policy landscape affecting the UK Further Education sector. Combined coverage across 200+ guides, 26 blog posts, and 15 named-college estate assessments.

Specialist topics
  • Salix Decarbonisation Loan bid mechanics
  • PSDS Phase 4 scoring and bundled bids
  • AoC Climate Action Roadmap implementation
  • FE Capital Transformation Fund + T-Level Capital integration
  • ESFA Post-16 Audit Code compliance
  • EAUC Sustainability Leadership Scorecard reporting

Every installer we match is accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Free · emailed within 2 working days

Get your college funding & feasibility summary

Tell us about your institution and we'll email a governor-ready funding & feasibility summary: which routes actually apply to you (Salix, PSDS, Great British Energy, mayoral and combined-authority schemes), an indicative system size and capex band worked from your electricity spend, and any red-flag eligibility issues. A desk exercise from what you send — no site visit needed to start.

What we won't do: pass your details to installers without your permission, add you to marketing lists, or ring you out of the blue — we don't even ask for a phone number.

Why we ask what we ask: your spend and postcode set the indicative system size, capex band and which regional schemes you can access — without them the summary would be generic. Reviewed by SEO Dons Editorial. We are an independent advisory, not an installer.