220 kW Solar + Air-Source Heat Pump Bundle — Bristol FE College, Modelled PSDS Phase 4 Bundle
- System size
- 220 kW
- Annual saving
- £56,000
- Payback
- 4.2 years
- Location
- Bristol, South West
Modelled example, not a completed installation. The college, people and figures below are illustrative and built from published scheme terms and benchmark costs; no named college or client is described. The funding stack shows how the schemes worked: as of 20 October 2026 PSDS Phase 4 is closed to new applications and Salix has no scheme open for England.
Scenario
A general FE college in central Bristol, serving roughly 6,800 16-19 learners plus a substantial apprenticeship and adult provision, sat on a campus dominated by a 1960s main teaching block and a 1980s annex. Both buildings were heated by ageing gas boilers approaching end of warranted life, and the college’s 2024-25 combined gas + electricity bill ran to £710,000 against a backdrop of South West regional electricity rates that had risen 31% in real terms since 2021.
The college’s Sustainability Lead, in post since the corporation adopted its Climate Action Plan in October 2024, had been tracking the Phase 4 application window for the Public Sector Decarbonisation Scheme (PSDS) since launch. The Phase 4 brief explicitly favoured integrated heat-decarbonisation + low-carbon-generation bundles over standalone solar — and the college’s gas boilers were close enough to end-of-life that the corporation could credibly include heat decarbonisation in the same bid.
The Phase 4 application was prepared as a bundled package: a 600 kW air-source heat pump array sized to replace the main and annex boilers, plus 220 kW of rooftop solar sized to offset a meaningful share of the new electrical load created by the heat pumps. The integrated economics were materially stronger than either intervention standalone — the heat pumps reduced gas demand and lifted electrical demand, and the solar took the edge off the new electrical demand and protected the long-run economics from electricity price drift.
This case study is an illustrative composite built from published scheme terms and 2026 FE college PSDS bundled-bid benchmark costs. It does not describe a single real installation.
The modelled design (solar element)
Total solar system: 220 kW across two roof envelopes, designed to integrate with the heat pump load profile.
- Main teaching block (south-east aspect membrane): 140 kW (256 × 545 W panels, 14° tilt, mechanically fixed, two string inverters in main plant room shared with the heat pump cascade)
- 1980s annex (south-aspect pitched tile): 80 kW (146 × 545 W panels, single string inverter)
- No battery on this scheme — the heat pumps act as a controllable load that follows generation, so PV-direct self-consumption modelled at 86% without storage and the corporation’s capital was prioritised on extending the heat pump array coverage
The heat pump element was scoped, costed and submitted under the same PSDS Phase 4 bid.
DBS-checked install crews across both subsystems. KCSIE 2025 safeguarding induction by the Deputy Principal at programme kick-off.
Funding stack — Modelled PSDS Phase 4 Bundle
This modelled scenario shows how a PSDS Phase 4 bundled bid was structured. PSDS Phase 4 is closed to new applications, so it is not a route a college can use today:
- PSDS Phase 4 grant: £880,000 covering the full bundled capex (solar £200,000 at £909/kW; heat pumps and ancillaries £680,000)
- Solar capital cost: £200,000 at £909/kW
- Modelled annual solar energy savings: £56,000
- Modelled annual gas-displacement savings (heat pumps): £142,000
- Combined modelled annual saving: £198,000
- Corporation capital contribution: zero in this model (it assumes the grant covers the full capex)
- Year-one cash position: £198,000 positive (no loan service, fully grant-funded capex)
- Total 25-year nominal benefit on the bundled bid: £5.4m (real-terms model, before gas price drift)
- Solar-element-only payback: 4.2 years (notional, against the grant value — actual corporation payback is zero years because PSDS is non-repayable)
The PSDS Phase 4 application leaned on the college’s published Climate Action Plan, the integrated decarbonisation rationale (heat + generation in one bid), the boiler end-of-life timing, and the DfE Sustainability and Climate Change Strategy alignment. Salix administered the PSDS application and confirmed acceptance in 13 weeks. Corporation approval was recorded in a single board minute under the Climate Action Plan agenda item.
Programme and compliance
- Summer 2026 build window: solar scaffold up 8 July; panels live 18 August; heat pump cascade commissioned in parallel and brought on-line 28 August, ahead of the autumn term heating-season start
- G99 DNO application: the bundled load picture mattered — the application went in with the heat pump electrical demand modelled alongside the solar export, so the DNO sized the connection upgrade once. Accepted at 15 weeks
- Asbestos R&D survey clear on the 1960s main block at roof level; one Type 3 enclosed protocol penetration on the 1980s annex
- Structural engineer survey on both roofs; the 1960s main block carried sufficient capacity for the panel array without strengthening
- Heat pump plant room sized in the same programme as the solar inverter cabinets, sharing controls infrastructure
- KCSIE 2025 safeguarding induction at every contractor mobilisation
- ESFA Post-16 Audit Code: PSDS grant drawdown lodged as an auditable workpaper; corporation board minute formally records the grant agreement
Outcomes
- Year-one actual solar generation: 5% above design model
- Year-one actual solar energy savings: £58,800 versus modelled £56,000 (+5.0%)
- Year-one heat pump performance: actual SCOP 3.1 versus modelled 2.9 (favourable winter weather pattern); gas-displacement savings landed at £155,000 vs modelled £142,000
- Combined year-one actual saving: £213,800 against the £198,000 model
- EAUC Scorecard: moved the college from “Silver” to “Gold” on the Operations and Estates module
- AoC Climate Action Plan reporting integration — both solar generation and heat pump runtime feed into the corporation’s quarterly KPI pack
- DfE Sustainability and Climate Change Strategy: the project was used as a featured case study in the regional DfE south-west FE cluster meeting in November 2026
- Phase 2 conversation: the corporation has opened scoping on a 90 kW car-park canopy under the next PSDS or Salix window, drawing on the same bid team